Challenges implementing planning & scheduling

  • 1.  Challenges implementing planning & scheduling

    Posted 05-04-2021 03:05 PM
    Hello All,

    I'm poring through the 4th Edition of Doc Palmer's Planning and Scheduling Handbook and am delighted by its pedagogy. I want to know if anyone has tried to formally implement a Planning and Scheduling program / group and what obstacles have you all encountered along the way. Did you see a 60% improvement in efficiency (turning 30 technicians into 47) as Mr. Palmer claims is attainable? What lessons have you learned?

    ------------------------------
    John Helwig
    Asset Management Consultant
    CDM Smith
    Kensington MD
    ------------------------------


  • 2.  RE: Challenges implementing planning & scheduling

    Posted 05-05-2021 07:33 AM

    John,

    We used a good bit from the Doc Palmer concepts for our P/S program development.  We also used a ton of industry practice as well.  The ideas behind the P/S calculation Doc provides is sound and does work.  The main focus you should have is getting the culture change accepted first.  This will make those calculations work.  If the buy in isn't there and they are not sticking to the best practices, then it won't go according to that.  Otherwise you will not see the results you seek.

    Using Doc's method we have shown how the program can be and we have been working toward it since.  We started our path about 2 1/2 years ago.  During this time we have shown the method to the managers and technicians routinely to socialize with them the needs for planning work.  Once we started doing this and analyzing some real world scenarios, with and without the method, we were able to show the progress.  It isn't fully there yet, since COVID occurred and kind of took us down a ladder rung or two.  However, the concepts are still being used.  We have been steadily getting it back into place, though, and are around our target goal of 30% increase in P/S efficiency.  An incremental improvement model will help to stay on track.  

    We also have shown the use of the calculation in identifying the number of planners needed within our group based on the efficiency we would like to be at.  This has given us a leg up on justifications with our execs.  

    Hope that is helpful. 



    ------------------------------
    Michael Guns, Jr., CRL, CEFP
    Associate Director, Maintenance Strategy & Planning
    University of Delaware
    Facilities - Buildings Maintenance & Operations
    200 Academy Street - Newark, DE 19716
    Maintenance Center - Room 113
    Office: 302.831.4055 Cell: 302.358.9381
    ------------------------------



  • 3.  RE: Challenges implementing planning & scheduling

    Posted 05-05-2021 08:32 AM
    Michael, this is very encouraging to hear, particularly in academia, which is the space my wife works (she is now Director of utilities at MIT). Thank you so much for sharing, and your feedback echoes the culture change / leadership drive that Terry mentioned.

    ------------------------------
    John Helwig
    Asset Management Consultant
    CDM Smith
    Kensington MD
    ------------------------------



  • 4.  RE: Challenges implementing planning & scheduling

    Posted 05-05-2021 08:14 AM
    Hi John,
    You have opened Pandora's  Box with your questions around implementing Planning and Scheduling. Many of us could talk for days about our experiences in implementing P&S. But I am going to keep this very short and to the point.
    1. It is a guarantee that you will encounter obstacles in implementing P&S. Some of these will be simple and some will be complex. But there are 2 major components for the implementation of P&S that are mission-critical to the success of any robust (i.e. successful) P&S or Work Management program. The first is the organization and its readiness for P&S. I'll start with the organization's support of the changes that are usually required. This is more than just agreeing that P&S is a good idea. It is truly managing and, most importantly, leading the change. The organization has to know and understand that this is not optional. If you don't have this leadership for the changes that are a part of P&S, I would tell you to not waste your time and  money to start. My experience is that more of these P&S initiatives only get a portion of the expected improvements than those that truly succeed. For those that succeed, the leadership is solid, supportive and they actually lead (or drive) the change. The second major component for success is having the right personnel in the right roles. And the Planner role is only one of those. But obviously it is a critical role. I've encountered poor choices made for Planners and they continuously struggle to do best-in-class planning. And I've seen Planners where managers made the right choices for their Planners and they are excellent. In those cases, the implementation usually goes well. You certainly want to make the right choices for Planners but others, e.g. Supervisors, Schedulers, OMCs, etc. are also critical for the overall Work Management system to work well.   
    2. Your other question was about improvements in efficiencies. The answer is Yes, these improvements are possible. And where these improvements are realized, go back and read #1. The readiness for change and the right people in the right seats has everything to do with the degree of improvements that are realized.

    ​

    ------------------------------
    Terry Taylor
    Taylor Reliability Consulting
    Raleigh, NC
    ttaylor@taylorreliability.org
    ------------------------------



  • 5.  RE: Challenges implementing planning & scheduling

    Posted 05-05-2021 08:29 AM
    Excellent synopsis Terry, thank you! You validated what I imagined is the biggest obstacle, support from above and staff commitment to it. This helps me when I espouse P&S virtues to my clients.

    ------------------------------
    John Helwig
    Asset Management Consultant
    CDM Smith
    Kensington MD
    ------------------------------



  • 6.  RE: Challenges implementing planning & scheduling

    Posted 05-05-2021 08:56 AM

    We can't argue against the value of planning and scheduling but John's question of 60 percent improvement of efficiency is valid.

    I have never been able to find any defensible statistical analytics to validate the claimed efficiency or most other claims made in our field of asset management. Hopefully, we will begin to adopt methods of validation now that it is possible. In this case of efficiency, at the least, we would draw upon what I call "difference" analytics such as some type of ANOVA or multilevel model to test that the difference is significant.

    Until we can statistically validate the ramifications of top-flight asset management, we will continue to struggle to gain management support.

    Richard G. Lamb, PE, CPA






  • 7.  RE: Challenges implementing planning & scheduling

    Posted 05-05-2021 11:26 AM
    Yes, my former organization based its improvement plans on that benchmark and achieved that level. We actually were planning on the converse where we leveraged planning and scheduling to achieve a 40% reduction in overall maintenance headcount while maintaining backlog. We can talk offline if you'd like more details on our experience. The biggest challenge is maintaining constancy of purpose with changes in management at facilities.

    ------------------------------
    Wayne Griffin
    Global Reliability Director
    Guardian Industries
    Auburn Hills MI
    ------------------------------



  • 8.  RE: Challenges implementing planning & scheduling

    Posted 05-06-2021 08:45 AM

    Wayne, Richard,

    Thank you for your contribution to this discussion. Indeed, the 55% comes form Doc Palmer - 30 technicians becomes 47, and that is based on his own observations throughout his career.

    But the consistent them I'm seeing in this conversation is leadership's support and commitment up and down the organization. It seems all of our technical know-how has been figured out for quite some time, but the people challenge will never go away and can never be overlooked.



    ------------------------------
    John Helwig
    Asset Management Consultant
    CDM Smith
    Kensington MD
    ------------------------------



  • 9.  RE: Challenges implementing planning & scheduling

    Posted 05-07-2021 11:03 AM

    Hello All,

     

    I see these efforts like I see going on a diet or quitting tobacco.  It is behavior change.  Behavior change is hard and you have to be motivated to make the change.  We understand the value and benefit of planning and scheduling.  We know and believe the consequences of not doing it (i.e. poor craft utilization, bloated inventories, reactive work is the norm, reliability impacts, etc).  The people that benefit the most from excellent planning, scheduling, and execution are not necessarily the persons doing it. It is operations and the organization as a whole.  A colleague used to talk about motivating through the use of sugar cubes and 2 by 4's.   Beach "bod" and better lung capacity are real and tangible benefits of changing behavior.  Perhaps some creative rewards could be used to motivate the change in addition to the necessary management support when the benefits are less tangible to individuals.

     

    Steve Carr

    Founder

    Symphonic Technologies






  • 10.  RE: Challenges implementing planning & scheduling

    Posted 05-12-2021 11:50 AM

    Hi John,

    You may experience pushback from execution. These are the folks that will be expected to carry out the plan. These are also the folks that may be used to operating in a reactive environment with less controls.  Implementing planning and scheduling is now guiding the supervisor how to address the maintenance issue. The plan and schedule will tell maintenance supervision the required parts/materials to be used, when they will work the activities, how long the job is expected to take and the required resources. Supervision will be expected to follow the plan.

    In my experience the craft in our facility that has been together the longest (the planners and the supervisors) is the most efficient. Why is that? they work as a team. They understand and respect each other's functions in their roles and communicate extremely well. The supervisors also understand the plan is a guide and is not always perfect. Yes, sometimes the scope of a repair will change requiring a new plan or supervision to be agile and requiring them to adapt on the fly. Of course adapting to the change will depend on how drastic the change in scope is. 

    Monitor and control the processes to identify and address gaps. Gaps aren't necessarily all that bad. A colleague and friend once told me, "There aren't problems, only opportunities for improvement!" I think he got this from his time in the Air force.  Develop ways to track things like the work orders and scheduling efficiency, different parts of your processes. Make sure you have the right meetings in place to support each functions success.

    Something we are working on is implementing feedback. Try to avoid the blame game if the plan is insufficient for some reason or if it could have been better. Have an avenue for supervision to provide feedback on the plan that will be reviewed by the planner. This supports continuous improvement and should help improve the job plan library as well. Feedback could include comments about the materials being correct/incorrect, if the BOM was incorrect and if activity duration/resources should be adjusted. Really anything that could improve the plan the next time around.

    Although planning, scheduling and work execution are different functions in the maintenance organization, if you can have them operate as a team I think this will lead to the greatest chance of success. Communication, planning and buy in are key! Good luck!



    ------------------------------
    Jason Weis PMP CMRP CRL
    Project Manager
    Monroe Energy
    Trainer, Pennsylvania
    ------------------------------



  • 11.  RE: Challenges implementing planning & scheduling

    Posted 05-18-2021 08:27 AM
    Very helpful Jason, thank you! Again, having this anecdotal perspective from you and others helps me convey the value of P&S to my clients - in other words, I can say "many other people have been here before and here is what they tell me."

    ------------------------------
    John Helwig
    Asset Management Consultant
    CDM Smith
    Kensington MD
    ------------------------------



  • 12.  RE: Challenges implementing planning & scheduling

    Posted 05-18-2021 09:36 AM
    One more point John. Implementing planning and scheduling is a huge change for an organization, make sure the project sponsors do not underestimate the change management required to support the success of the project. Planning to engage the folks that will be impacted by the change early in a project will increase your chances of a successful implementation.  

    I just watched a webinar titled Understanding Change Resistance – Avoid resistance, don't cause it by Ross Wirth on PMIs web site. I highly recommend giving it a look (if you have access) as it contains some very good information on understanding and managing change. 

    Take care,
    Jason

    ------------------------------
    Jason Weis PMP CMRP CRL
    Project Manager
    Trainer, Pennsylvania
    ------------------------------



  • 13.  RE: Challenges implementing planning & scheduling

    Posted 05-18-2021 10:16 AM

    How much of the struggle to implement planning and scheduling is because the world of maintenance does not do workload-based budgeting as should be done for any type of operation? When the budget process quantifies the number of jobs to occur monthly and annually, it follows that we can quantify the number of planners and schedulers needed to prepare and execute work in a manner that will sustain the production process. If I were management, you had better come to me with that information if you want me to support your vision for planning and scheduling.








  • 14.  RE: Challenges implementing planning & scheduling

    Posted 05-19-2021 06:26 AM
    John, I have been involved in dozens of planning and scheduling implementations. I have read through all of the other responses and they are great. People Change, quality planner, etc. The common theme in the difficult installations I have been involved with is lack of "real" support from upper management. The typical reason for this is a lack of understanding about what maintenance planning, in particular, is really like. Most higher level managers come from a business and product manufacturing background so their mindset tends toward reactive. "We need it done now" is the common mantra. Managers need to be helped to understand what Planning and scheduling really is.
      I was involved in racing motocross as a teenager and my dad said something that has stuck with me to this day. You have to go slower to go faster. Taking the corner just right is faster than trying to go through at top speed. The line is wrong, there is a higher chance of messing up and being technical will prove most times to be faster that all out and on the edge of out of control. The same goes with planning. Having all of the parts of the job planned and ready to execute is much more efficient (faster) during execution than trying to cobble together a reactive job plan where mistakes are common. You have to go slower to go faster. There are certainly times when, during a (real) emergency steps must be taken to mitigate danger to life and the environment but with professional planning, good quality PM's, and a well trained planner, emergencies will become more rare.

    ------------------------------
    Howard Corley
    Senior Consultant
    Life Cycle Engineering
    Deatsville AL
    ------------------------------



  • 15.  RE: Challenges implementing planning & scheduling

    Posted 05-21-2021 03:52 AM

    Hello John, I have to agree with Howard, I worked in the aviation industry where in the late 1990s most planning and scheduling was done via a manual review of an aircraft cardex system, needless to say this led to many missed maintenance task that ended in aircraft groundings at the most inopportune times and fines from the aviation authority.

     

    Senior management must be in 100% in support of your planning and scheduling program in order for it to work. Additionally your planning and maintenance / production managers must being co-equal in assigning, reviewing and confirming why works must be done at their pre-set times.

     

    In my case I was able to see a reduction in staff headcount, but the tremendous savings came from over 60% efficiency (increase) in aircraft uptime, almost 40% reduction in maintenance downtime, and overall improvement in M&E operating cost.

     

    This is what executive management expects of us.

     

    Lunnon Gibson, B.Sc. ME, MBA,

    Reliability Systems International

     

     

     

     

     

     

    Sent from Mail for Windows 10

     






  • 16.  RE: Challenges implementing planning & scheduling

    Posted 06-03-2021 08:22 AM
    Great anecdote - thank you Howard!

    ------------------------------
    John Helwig
    Asset Management Consultant
    CDM Smith
    Kensington MD
    ------------------------------



  • 17.  RE: Challenges implementing planning & scheduling

    Posted 05-29-2021 09:36 AM
    John,

    Doc's numbers are achievable, and have been achieved/exceeded. I worked with several research universities and achieved those results. The University of Central Florida (UCF) won an Uptime Award from ReliabilityWeb in 2015 for best work management program. The first higher Ed facilities organization to receive that award.

    As most have pointed out, achieving success is 90% dependent on leadership accountability. While some organizations with solid leadership accountability can be successful, many try to implement with a leadership team that has not been required to have leadership accountability. This is akin to Einstein's doing the same thing and expecting different results. 

    For orgs without good leadership accountability, bring in outside support that can provide coaching that instills leadership accountability. Preferrably outside support that has a plan to taper off their support as the organization's leadership team demonstrates leadership accountability competence and confidence.

    Best regards,

    ------------------------------
    Tom Moriarty
    President, Alidade MER, Inc.
    Satellite Beach FL
    http://www.alidade-mer.com
    tjmpe@alidade-mer.com
    ------------------------------



  • 18.  RE: Challenges implementing planning & scheduling

    Posted 05-31-2021 08:31 AM

    Tom, please tell us how the statistical analysis was conducted. We should never accept the results of a study without knowing how it was structured as an experiment.






  • 19.  RE: Challenges implementing planning & scheduling

    Posted 05-31-2021 09:48 AM
    Richard,

    I appreciate your diligence in working to strengthen the foundation of our profession. The question posed by John was whether anyone had implemented Doc Palmer's practices, if so, has a 60% improvement in labor effectiveness been achieved and what lessons have been learned. I'm not sure what you're asking in terms of statistical analysis. If you mean having a large sample size of organizations, each following Doc's methods and then doing peer reviewed statistical analysis, I don't know of anyone doing that. I suppose a study could be conducted that looks into all the papers presented at SMRP annual conferences, review the P&S methodologies for compliance with Doc's book and then analyze the data presented to get the statistical information.

    There has been at least one study (by Winston Ledet) that showed the implementation of PM/PdM programs and reliability programs without planning and scheduling was actually counter productive to availability. PM/PdM programs and reliability programs with P&S increased availability. That study was done before Doc's book was published, however the basics of planning and scheduling are what is important. Doc doesn't propose anything exotic; he does provide a very practical approach to defining and implementing P&S. 

    At the end of the day, if I'm a plant manager or maintenance manager, I want to know if it will work. Empirical data. Doc's methods have worked in manufacturing, utilities, government agencies, higher education, etc. It works because good planning and scheduling is simply putting good guidance in place, providing what's needed to carry out the guidance (training and tools) and having leadership accountability to implement and sustain compliance. It's not magic. 

    The observable outcomes can be shown in a suite of measures (using SMRP's metrics) such as:

    • Total labor hours available
    • Percent of work scheduled
    • Percent schedule compliance
    • Percent of labor allocated to PM/PdM
    • Percent PM/PdM compliance
    • Percent corrective maintenance
    • Percent reactive maintenance
    • Average number of work orders completed per person per day

    In the case I mentioned, the facilities maintenance team average number of work orders completed per person per day went from 1.4 to between 4.8 and 5.4 (depending on the zone). A percent increase in that metric of 271% (using 5.2 average). 

    Leadership accountability is needed to establish that level of performance. Leadership accountability is needed to sustain that level of performance.

    ------------------------------
    Tom Moriarty
    President, Alidade MER, Inc.
    Satellite Beach FL
    http://www.alidade-mer.com
    +1 (321) 773-3356
    tjmpe@alidade-mer.com
    ------------------------------



  • 20.  RE: Challenges implementing planning & scheduling

    Posted 05-31-2021 10:23 AM

    Tom, By statistical analysis I mean the practices to determine what truly happens by virtue of planning and scheduling. I thought you meant that USF had conducted such analytics. I can presume by your response that we of asset management have still not accomplished that insight. If we did we would likely get some serious management support for P&S.






  • 21.  RE: Challenges implementing planning & scheduling

    Posted 06-03-2021 08:24 AM
    Tom, very insightful, thank you. I think outside support to challenge the groupthink and status quo seems to help galvanize people to go on the journey. Great insight.

    ------------------------------
    John Helwig
    Asset Management Consultant
    CDM Smith
    Kensington MD
    ------------------------------



  • 22.  RE: Challenges implementing planning & scheduling

    Posted 06-17-2021 09:46 AM

    The obstacles are many, and the results vary.  Even the most reactive plants will sometimes do an excellent job of planning and scheduling some particular large repair, and some plants with planning and scheduling systems in place don't use them particularly well (but with better results ongoing than those with none).

    65% wrench time is a target, but many pieces have to be in place to get there and to stay there consistently. But it isn't necessary to get all the way there to make staffing the planning position worthwhile.  If a planner is put in place to support ten technicians, then their wrench time productivity only has to increase from 35% to 39% to justify the position, not all the way to 65%. And that much improvement is pretty easy.
    All those extra technicians won't show up on day one of implementing planning but somebody will, some of the time, and more will follow.

    The choice is simply that of choosing to do maintenance on a disorganized, immediate response basis, or of doing on an organized, managed basis. It would seem to be an obvious choice, but many in industry don't even seem to know that maintenance can actually be done on an organized basis. So plant wide education is a primary requirement.

    The other major piece is prior knowledge of developing equipment issues before they need an immediate response, so that there is time for planning and scheduling to actually happen. Various kinds of Preventive Maintenance Inspections have to be in place first for planning and scheduling to show real results.



    ------------------------------
    John Crossan
    Manufacturing Maintenance Consultant
    John Crossan Consulting
    Downers Grove IL
    ------------------------------



  • 23.  RE: Challenges implementing planning & scheduling

    Posted 06-17-2021 10:45 AM
    Excellent post John. I would encourage everyone to remember the ratio of 3:1. For every hour a planner spends doing effective planning, the return is a savings of 3 hours during the execution of the task or an equivalent savings in material dollars.

    ------------------------------
    Howard Corley
    Senior Consultant
    Life Cycle Engineering
    Deatsville AL
    ------------------------------



  • 24.  RE: Challenges implementing planning & scheduling

    Posted 06-18-2021 08:43 AM
    The role of the planner is key to becoming more organized.  If the company and maintenance manager truly supports the concept of planning and scheduling then the planner has the opportunity to lower the burden over time by only planning each job once.  A planned job has parts, labor, special equipment and safe work procedures identified and built.  By creating Standard Jobs/Task Lists (or whatever terminology your CMMS uses to build a work order template) for every job performed, then first searching for a Standard Job before starting the process of planning, the planner can greatly reduce the effort required to plan.  Over my career I've had several roles as a planner and saw many planners not doing this and working a lot harder to get their work done.

    ------------------------------
    Peter Morris
    Managing Director
    MCSPRO
    Heber City UT
    ------------------------------



  • 25.  RE: Challenges implementing planning & scheduling

    Posted 06-22-2021 01:58 PM

    I agree with you Peter, as the Maintenance Planning Manager, I had to make significant adjustments and discussions with the Maintenance team to have them understand the intricate and complex arrangements that had to be altered each time to developing a work package for aircraft coming in for maintenance. As a Reliability Engineer my experience in that arena assist me greatly, but having great communications with the Maintenance Manager (and his lead team of engineers) and permitting them to see the package weeks before issuance permitted a much improved maintenance downtime and a higher percentage of work completed.

     