David, as a consultant in this field, there are two things I look at to see if maintenance staffing is in the ballpark: work backlog (in person-weeks) and the ratio of Replacement Asset Value per craftsperson. Backlog is by far the more accurate measure; the craft resources have to be balanced with workload or Covey's quadrant 2 work (important but not urgent) will not get done. The level should be maintained between 4 to 6 weeks. I find that the ratio of RAV to craft is around $5,000,000 in poorly managed operations and about twice that in very well-run operations.
Of course, the definitions of all the factors are available from SMRP, free to members.
Hope this helps,
Bruce
Bruce Hawkins, CMRP, CAMA | Director | Operational Certainty Consulting
Emerson Automation Solutions | 1100 Louis Henna Blvd.| Round Rock | TX | 78681 | USA
M 843 743 5962
Bruce.Hawkins@Emerson.com
The information in this electronic mail message, including any attachments, is intended solely for the use of the individual(s) to whom it is addressed and may contain information that is privileged, confidential, or otherwise exempt from disclosure. Access to this Internet electronic mail message by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or action taken or omitted to be taken in reliance on it is prohibited and may be unlawful. If you have received this communication in error, please destroy this communication and notify the sender immediately. Thank you.
------Original Message------
Although I've found great ideas and experience on ratios of RE/Techs, ME/Techs, or MM/Techs, I haven't been able to find staffing ratios for hourly Maintenance Techs to Plant or industry. I understand there are variables that impact this ratio, such as current skill-sets of craftsmen, maturity of the organization and team, development and use of processes and repeatable procedures, and the degree to which we are reactive or proactive.
We are a young food processing plant, with the honeymoon of inherent reliability ending. We've built maintenance methods from the ground up, and in the beginning, had to accept less-than-hungry Technicians. As our team is leveling off, and the pruning continues, I feel more excited about our future than ever before. We're blessed to have steady business during these changing times, and I continue to make business cases for additional staff. As I campaign for hiring to fill key roles, the conversations are difficult due to hiring freezes, or at least hiring restrictions during this period of shelter in place.
Further constraints are improper initial hierarchy setup, no CMMS SME on site, and no Maintenance Planner. Getting clean data in, and actionable reports out is excruciating. Therefore, running reports that would assist in my business cases is absent. We are using M3 by infor for our CMMS. I'm looking for sources or benchmarks from the M&R community that would help me underscore proper staffing levels. Even templated worksheets would give me a launch pad. One metric I remember seeing was hourly techs/plant hourly employees. Seems like that ranged from 15% to 30%, depending on industry. Even 15% seemed high to me. By that metric, I'm currently staffed at 3.7%.
All inputs are very appreciated. Thank you.
------------------------------
David Smith, CMRP, REC
Plant Maintenance Manager
Daily's Premium Meats
------------------------------