  • 1.  Benchmark Target Changing for MRO Inventory %ERV ?

    Posted 05-04-2023 11:14 AM

    Should the Benchmark Target for MRO Inventory as % ERV change in the post-covid, disrupted Supply Chain environment we're in today?  Even with early warning from the effective use of Predictive Maintenance technologies, Spare Parts and Equipment are taking longer to acquire than the early warnings of failure provided by PdM, making larger inventories of spares a necessary strategy for equipment and process reliability.


    This communication is for use by the intended recipient and contains information that may be Privileged, confidential or copyrighted under applicable law. If you are not the intended recipient, you are hereby formally notified that any use, copying or distribution of this e-mail,in whole or in part, is strictly prohibited. Please notify the sender by return e-mail and delete this e-mail from your system. Unless explicitly and conspicuously designated as "E-Contract Intended", this e-mail does not constitute a contract offer, a contract amendment, or an acceptance of a contract offer. This e-mail does not constitute a consent to the use of sender's contact information for direct marketing purposes or for transfers of data to third parties.


    Francais Deutsch Italiano Espanol Portugues Japanese Chinese Korean

    https://www.dupont.com/email-disclaimer.html


  • 2.  RE: Benchmark Target Changing for MRO Inventory %ERV ?

    Posted 05-05-2023 11:14 AM
    Timothy
     
    Short answer - probably, given the potential delay in access to spares.  However, a more important issue to be considered is the nature of your maintenance function.  If you're highly reactive, you need a lot of spares, since you don't know what's needed next. If you're more PM/PdM driven then fewer, since you have a greater understanding of what's needed and when, but your best position is one where you're very proactive about eliminating the defects that create the work, and need for spares.  Fewer failures = fewer spares, and when linked to a solid PM/PdM program, allows for better management of spares requirements, IF you run your storeroom like a business - clean efficient, quantities linked to use rates, etc.  I would hold the stores/purchasing manager and maintenance manager both responsible for inventory levels/turns, and, service levels (stock out rate).  It facilitates a more collaborative relationship, and better system-level result.  I hope this helps.  
     
    Ron Moore