Hi Deepak,
I am not CMRP but am working towards it however I will give my opinion on the matter.
I believe you want to know if you had a whole plant loss of power would you include this unavailability in your sub-equipment availability (asset) calculations?
I would not include this. Maintenance and reliability best practices state availability is the probability that an asset is capable of performing its intended function.... It later states that availability is a function of reliability and maintainability of the asset. It is for this reason I personally would only consider asset availability not the whole plant failure in your calculations.
Another way to think is that availability is calculated by (MTBF)/(MTBF/MTTR). If MTBF is the operating time over number of failures then it would not include the whole plant loss of power as it could not be operated.
You also would be looking to address the availability of an asset with which the fault lies elsewhere hence giving false work to address.
Final point is that if you include total power failure on every single asset then in turn it becomes irrelevant because you will reduce every single assets availability percentage and not achieve anything than a lower availability and OEE etc..
In short; my own personal opinion is to not include it for availability metrics but do consider it other tools i.e. FMEA, RCA, etc. again I hope someone else will share their thoughts as I am not actually CMRP and would like to hear feedback and thoughts.
Kind regards
Keiron.
------------------------------
Keiron Arndell
Cheshire
------------------------------
Original Message:
Sent: 07-08-2020 12:46 PM
From: Deepak Dili Vasumathi
Subject: Regarding unplanned downtime calculation for system and subsystem
Hi Guys,I would like to get all of you valuable comments on the below query:
Query:
Lets assume my Plant as a system is having 10 sub-equipment.
If a failure of a total plant (for e.g. Power Failure) will be an unplanned downtime for my Plant with some Corrective Maintenance Downtime.
So my question is when I consider my sub-equipment for availability calculation (individual equipment wise calculation) should I consider the same failure's downtime as an unplanned downtime/corrective maintenance downtime for the equipment as well.
Regards
------------------------------
Deepak
------------------------------