For prioritizing corrective maintenance work, we currently select 0-2 weeks (schedule break-in), 2-7 weeks (expedited), and so on, based on typical Oil & Gas consequence & likelihood criteria. Within SAP work requests, the system will populate a "required end date" (RED) based on the latest date in the selected priority period- i.e. select expedited and the system will populate an RED of 7 weeks from today.
We are experiencing RED manipulation (which is a process issue) where the user manually populates a date much earlier in the period. Does anyone have any data to suggest the impacts of performing maintenance in a 2-4 week period vs a 4-8 week period? We are trying to build a case of introducing another priority category (2-4 weeks) in order to understand the impact of short-term work and its frequency. This data is difficult to extract- i.e. We require data analytics to determine when the RED is manually entered vs allowing the system configuration.
Industry generally agrees that reactive maintenance is significantly more expensive than proactive…however, can anyone offer their experience regarding better categorization of short-term work? i.e.- As you can see, setting an RED of 15 days (in reality a break-in) vs 7 weeks (where we can utilize normal Planning, Scheduling, & Execution process) within the "expedited" category seems to large a period. Sorting the work orders by priority leads to skewed data- i.e. The perception is that our expedited work orders were requested to be completed within 7 weeks while in reality, many were manipulated to between 2-4 weeks.
Consider the following constraints:
1- we do not want to introduce SAP configuration that does not allow manual RED manipulation (due to instances where it is warranted)
2- introducing a new priority sounds simple, however, it requires significant SAP & related system impact studies to avoid an unwanted consequence
3- we know that the date manipulation results in increased material delivery costs, pressure on P&S, execution resources and related increased inefficiency, not to mention the increased safety exposure with less planful, reactive work…question is…how significant?
Bottom line- Looking for any input/experiences to evaluate the worthiness of this change vs the risk we are exposed to…and the effort it will take to facilitate.
------------------------------
Abrar Ahmad
Specialist, M&R Advisor
Suncor Energy Inc
Calgary AB
------------------------------